第74题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent Y260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent Y300,000 by this point. Based on these circumstances, your project could be best described as ( ).